UK electricity 2025/26 capacity auction clears at 30.59 pounds/kW/yr

Updated : Feb 23, 2022, 10:08 UTC1min read
(Reuters) – Britain’s auction to ensure enough electricity capacity for 2025/26 has cleared at a 30.59 pounds ($41.54) per kilowatt (kW) per year range, National Grid said.
Most Popular

(Reuters) – Britain’s auction to ensure enough electricity capacity for 2025/26 has cleared at a 30.59 pounds ($41.54) per kilowatt (kW) per year range, National Grid said.

A total quantity of 42.36 gigawatts (GW) of capacity was procured, National Grid said.

Advertisement
Know where Markets is headed? Take advantage now with

Your capital is at risk

Britain launched its power capacity market in 2014, offering to pay providers for making supplies available at short notice.

Britain usually holds auctions for power capacity about four years in advance of the delivery date and another auction for a smaller amount of capacity around a year before delivery.

Out of the total 42 GW procured, 27.6 GW was from gas-fired power plants, nearly 7 GW from interconnectors and 2.5 GW from pumped storage, and the rest from other sources, a provisional auction document showed.

About 76% of the capacity procured in the auction was from existing power assets, the auction results showed.

Utilities such as Centrica, Uniper, SSE, Drax Group and E.ON were among winners of agreements.

SSE said in a statement on Wednesday that it had secured contracts from Oct. 1, 2025 to Sept. 30, 2026. at the capacity auction.

The contracts comprised 912 MW of hydro-electric and pumped storage capacity and 2.6 GW of gas-fired capacity from its Peterhead, Marchwood and Keadby 1 power stations.

Drax Group said it procured 621 MW of capacity agreements for pumped storage and hydro assets.

($1 = 0.7364 pounds)

(Reporting by Brijesh Patel in Bengaluru and Marwa Rashad in London; editing by Nina Chestney)